CPM1 Critical Path Analysis Critical Path Analysis ex) 1. ES (earliest start) - Earliest start time given predecessor activities 2. EF (earliest finish) - Earliest possible completion time 3. LS (latest start) - Latest start time as to not delay entire project 4. LF (latest finish) - Latest finish time as to not delay entire project 1) Forward Pass - Proceed through diagram from strat to finish 다이아그램의 시작부터 시간을 계산해 나감 - ES.. 2024. 3. 5. 이전 1 다음